Remynse Resources


Information and Links:

´¡»å»å°ù±ð²õ²õ:Ìý Ìý ÌýÌý



STEM, STRINGS & VESTIBULE
Phase: Two

Architect:ÌýHahnfeld Hoffer Standford

Construction Manager: W.B. Kibler

Start Construction:ÌýWinter 2016
Finish: Fall 2017



LIFECYCLE & DEFICIENCY
Phase: Five

Architect: VLK Architects

Construction Manager: Phillips | May Construction

Start Construction:ÌýSpring 2019*
Finish: 2019*
*Dates are projections and subject toÌýchange.


 

 

Project Status: Complete

Construction for the first bond project at Remynse - the two new STEM labs, strings room and security vestibule - is complete.

The second bond project at Remynse - lifecycle and deficiency work - is complete now as well. Scope included new fiber cabling, new chiller and boiler, new HVAC roof-top units and a new fire alarm system.


Project Scope

Bond-funded work at Remynse is being done in two stages. The first stage includes adding two STEM labs, a strings room and security vestibule. The second stage includes a number of life-cycle and deficiency upgrades.

  • Add 2 STEM labs
  • Add strings classroom
  • Add secure entry vestibule
  • Upgrade technology connectivity
  • Improve existing site accessibility
  • Add additional card access controls
  • Repair/replace and upgrade heating and A/C, plumbing, interior finishes, playground and landscaping
  • Upgrade security cameras and PA system (to be done by ¼«ËÙÁùºÏ²Ê security and technology departments)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.